- News
- Books
Featured Books
- smt007 Magazine
Latest Issues
Current IssueIPC APEX EXPO 2024 Pre-show
This month’s issue devotes its pages to a comprehensive preview of the IPC APEX EXPO 2024 event. Whether your role is technical or business, if you're new-to-the-industry or seasoned veteran, you'll find value throughout this program.
Boost Your Sales
Every part of your business can be evaluated as a process, including your sales funnel. Optimizing your selling process requires a coordinated effort between marketing and sales. In this issue, industry experts in marketing and sales offer their best advice on how to boost your sales efforts.
The Cost of Rework
In this issue, we investigate rework's current state of the art. What are the root causes and how are they resolved? What is the financial impact of rework, and is it possible to eliminate it entirely without sacrificing your yields?
- Articles
- Columns
Search Console
- Links
- Events
||| MENU - smt007 Magazine
Why the Right Preparation is Crucial for Your NPI
February 15, 2018 | Neil Sharp, JJS ManufacturingEstimated reading time: 3 minutes
Taking a new product design from conception to reality is a hugely exciting prospect for any original equipment manufacturer (OEM), whether you’re planning to bring a brand-new prototype to market, to up-issue an existing design, or to transfer your outsourcing requirements to a new assembly partner.
In today's increasingly competitive manufacturing environment it's crucial that you are able to produce high quality new products that can be delivered on time, at the volumes required and at the right cost. And the key to ensuring a smooth transition from the initial design through to final manufacture is the implementation of a new product introduction (NPI) process.
If your electronics manufacturing services (EMS) provider gets each stage of the NPI process right, then you could be on track to boost sales, encourage company growth and achieve lucrative market share. But if you fail to complete your project on time, within budget or to the required standard then it could be a completely different story.
Critical to the success of your NPI process will be the rigorous behind-the-scenes preparation work that your EMS partner puts into action before the build of your product even gets underway.
In this blog post we explore the vital importance of preparation for NPI, and what you can (and should) expect of your EMS provider throughout this essential stage.
Of course, no two EMS partners are the same. Each will have their own unique assembly equipment, build documents, internal procedures and staffing capabilities. And each is likely to have their own approach as to how they manage the process of NPI within their manufacturing environment.
What's crucial though is that your EMS partner provides you with complete transparency as to how they manage each stage of this complex process and that they can clearly demonstrate the quality controls that they have in place.
Preparing for the Build
A huge amount of detailed behind-the-scenes work needs to take place before your NPI build can even begin. Your EMS will kick off the process by quoting the product, loading the bill of materials (BoM) onto their system and acknowledging the order. They'll then move on to procuring the materials, taking delivery, inspecting them and assigning them to a unique works order.
Your EMS provider's engineering team, meanwhile, will be responsible for checking the PCB panelization, setting up the programs for pick-and-place and AOI machines and for creating custom-built packs for the production teams to work to.
All the materials for the job will then need to be prepared for assembly - from baking bare boards to draw out moisture, to cropping component legs for through-hole placement (PTH) and the loading of pick and place feeders with surface mount reeled devices.
Your EMS partner will ideally capture all of these tasks in a 'tollgate' process which will culminate in a pre-build review meeting controlled by their engineering team. It's vital that everything is in place before the build begins. So, as an example, the logistics team shouldn't be in a position to release any material out to the production team until engineering gives the final approval.
Your EMS partner may also insist on creating a small batch first before they even consider moving on to 'production' volumes. Testing your NPI build in small batches can be invaluable in ensuring that any errors in the build information or the build process are identified and nipped in the bud to avoid any time-consuming and costly rework further down the line.
While the NPI process is a necessarily complex one, many of the tasks and procedures that your EMS partner will carry out may not always be so obvious to you as the OEM. And to some extent of course, they probably don't need to be.
After all, what's most important to you as the customer, is that your products turn up on time, in budget and in full working order.
Ultimately though, the quality and robustness of the NPI process that your EMS provider has in place, will be a critical contributor to your success, from the initial pre-planning stages right through to the final delivery of your new product.
This article originally appeared on the JJS Manufacturing blog, which can be found here.
Suggested Items
Mek's Next-Gen AOI Technology Takes Center Stage at IPC APEX EXPO 2024
03/19/2024 | MEKMek is excited to announce its presence at IPC APEX EXPO, North America's largest electronics manufacturing event, in Anaheim, California, from April 6-11, 2024. Attendees are invited to visit Mek at booth #1433 to explore the latest AOI technology offerings.
New Features Boost Speed, Accuracy, Ease of Use for YAMAHA AOI System
03/18/2024 | Yamaha Robotics SMT SectionYamaha Robotics has announced Performance-boosting upgrades for the YAMAHA YRi-V 3D AOI system. These upgrades include faster board handling, multi-component alignment checking, and enhanced LED coplanarity measurement, among others.
Saki to Unveil Cutting-Edge Inspection Innovation to US-Market at IPC APEX EXPO 2024
03/14/2024 | Saki CorporationSaki Corporation, an innovator in the field of automated optical and X-ray inspection equipment, will be exhibiting at IPC APEX Expo 2024 in Anaheim, CA USA from April 9-11.
MIRTEC to Showcase State-of-the-Art 3D AOI Solutions at APEX 2024
03/11/2024 | MIRTECMIRTEC, ‘The Global Leader in Inspection Technology,’ will showcase its complete line of 3D AOI and SPI Inspection Systems at Booth #2100 during the 2024 IPC APEX EXPO scheduled to take place April 9-11, 2024, at the Anaheim Convention Center.
ViTrox Makes a Comeback: Experience the Latest Innovations at IPC APEX EXPO 2024
02/29/2024 | ViTroxViTrox, which aims to be the world’s most trusted technology company, is thrilled to announce its return to IPC APEX 2024, the largest electronics manufacturing event in North America. ViTrox eagerly invites visitors to explore our offerings at Booth #2642, Anaheim Convention Center, LA, from April 9th to 11th. During this time, we will unveil a series of cutting-edge inspection solutions poised to revolutionize manufacturing production lines.